Road Closures
Final Paving Operations for Hand Avenue from Nova Road to US1 are scheduled to occur starting Monday, November 18, 2013, and continue through Friday, November 22, 2013.

The contractor will maintain one lane traffic in work areas as work progresses.  Expect delays during this final construction phase of the project.

View Notification of Street Closure

Effective Monday, April 29, 2013, Hand Avenue will be closed to ALL through traffic from the east end of the 600 block (newly paved area at Central Park) to Center Street.

Residents in the 500 block of Hand Avenue will be allowed access west of Center Street.  This road closure is necessary to begin the construction of the canal crossing Hand Avenue connecting Central Park Lake North with Central Park Lake South.

All residents from the 600 block and to the west towards Nova Road must enter and exit to the west.  All residents from the 500 block east towards US 1 must enter and exit to the east.  There will be NO through traffic at Central Park on Hand Avenue for the next 5-6 months.

If you have any questions of concerns, please contact the City's Resident Project Representative, Ed Gard, at (407) 539-4515. 

View notification and map of road closure.

Hand Avenue from 500 fest west of Coolidge to Center Street will be closed from January 28, 2013, through May 28, 2013.

The City will be constructing utility improvements and roadway upgrades.  Additionally, the 600 block of Hand Avenue, from the west side of Central Park to Oakbrook Drive, will see the completion of the roadway upgrades by the end of February 2013.  Access for residents in these two areas will be maintained.  All other traffic is encouraged to follow designated detours on Fleming Avenue and Division Avenue.

This is the third and fourth in a series of phased detours associated with the improvements on Hand Avenue between US 1 and Nova Road. Future notices will be issued as the construction area shifts to the final phase of construction from Center Street west through Central Park.

If you have any questions regarding this closure, please contact the City of Ormond Beach Engineering Department at (386) 676-3269. 

Hand Avenue from Nova Road to midway between Oak Brook Circle will be closed from August 20, 2012, through December 17, 2012.

The City will be constructing roadway upgrades and utility improvements. Please use designated detours. This is the second in a series of phased detours associated with the improvements to Hand Avenue which are scheduled to occur from US 1 to Nova Road. The first phase closing of Hand Avenue from US 1 to 500 feet west of Coolidge Avenue will remain closed until September 14, 2012. Future notices will be issued as the road closure areas shift with construction.

If you have any questions regarding this closure, please contact the City of Ormond Beach Engineering Department at 386-676-3269.


Hand Avenue from US 1 to 500 feet west of Coolidge Avenue will be closed from June 18, 2012 through September 14, 2012.  

The City will be constructing roadway upgrades and utility improvements. Please use designated detours.  

This is the first of a series of phased detours associated with the improvements to Hand Avenue which are scheduled to occur from US 1 to Nova Road.  Future notices will be issued as the road closure areas shift with construction. 

If you have any questions regarding this closure, please contact the City of Ormond Beach Engineering Department at 386-676-3269. 

View Notification of Road Closure